Central Petroleum Limited (ASXCTP) Market Update on Other Properties


Http://www.abnnewswire.net/rss2/menafn/abn_menafn_en.asp

Following the completion of the acquisition of the Palm Valley and Dingo gas fields from Magellan yesterday, Central Petroleum Limited (ASX:CTP) (OTCMKTS:CPTLF) ("Company" or "Central") provides the following update on our other properties



Surprise Wes



The first 7 days of production at Surprise West was 3,668bbls or 524bopd average. Whilst the down hole pump has been successfully installed it will not contribute to the production rate until the average approaches 450bopd



Further to the issuance of the Production Licence, the earthworks necessary for the installation of the additional storage tanks and ancillary equipment has been completed. The Company expects that these storage tanks and ancillary equipment will be fully operational in May



Surprise Eas



As advised, circumstances required Central to give up our March drilling slot in February and we now expect that the rig will become available in the second half of the April Quarter



Mt Kitt



The Santos operated Ensign 918 drilling rig mobilised to Mt Kitty. After completing a planned routine maintenance the rig commenced rigging up on the well. The initial drill out of the 9 5/8" casing shoe that had previously been set at 785 meters has been completed and the rig is preparing to drill ahead to a planned TD at 2,033m



Southern Georgina Joint Ventur



Despite extensive flooding around the expected drill sites in February and March the Company still anticipates drilling to commence in the second half of the April Quarter.


Legal Disclaimer:
MENAFN provides the information “as is” without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the provider above.